Construction Update - 4/22/2021


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (4/19/21 to 4/24/21) scheduled work activities:

G2/G1

  • Drywall Framing for non-priority walls underway G-2

  • Overhead MEP installation continues – G-2 & G-1

  • Concrete equipment pads poured on G- 2.

  • Chiller plant piping installation continues on level G-1.

Level 1

  • Installation of glazing and frames for exterior glass continues on North Tower.

  • Overhead branch HVAC duct installation underway.

  • Anchoring & Horizontal Frame installation South Tower.

  • Installation of Fire suppression piping NW Tower.

  • Installation on Stairs underway.

  • Installation of West Bridge steel underway.

Level 2

  • Sheet metal HVAC ductwork rough-in continues.

  • Poured concrete on top of metal decking of center & West bridges.

Level 3

  • Removal of timber shoring on Level 3 pour areas 1.

  • Continued installation of structure of center bridge.

Level 4

Shoring timbers in place.


Level 5

  • Shoring timbers in place.

Level 6

  • Concrete pour level 6 area 3.

  • Placing and setting columns Level 6 area 4.

  • Concrete poured level 6 area 4.

Mechanical Penthouse

  • Forming/placing of rebar for in area 6-1 continued.

  • Concrete pour in area #1 on 4/21/21.

Site

  • Pouring of Concrete slabs and pads for generator yard equipment installation.

  • Delivery of Micro-Grid equipment on 4/21 & 4/22.

Next week's (4/26/21 to 5/01/21) scheduled work activities:

G2 & G1

  • Drywall framing non-priority walls G-2.

  • Framing of Dispensing/Air lock and Hot cell walls.

  • Overhead MEP installation continues G2 & G1.

  • Installation of pre-action system at Cyclotron G-2.

  • Concrete equipment pads poured on G-2.

Level 1

  • Framing walls south tower.

  • Installation of fire suppression piping South tower.

  • Detailing stairs in North tower

Level 2

  • Overhead MEP Installation continues.

  • Framing exterior windows - North tower.

  • Steel bridge erection, setting out riggers on Level 2 East bridge.

Level 3

  • Frame exterior windows – North Tower.

  • Overhead MEP work continues.

Level 4

  • Installation of metal decking and studs on bridge

  • Begin removal wood reshores.

Level 5

  • Setting of West bridge main elements.

  • Begin removal of wood reshores.

Level 6

  • Installation of columns for level 6 roof/floor of mechanical penthouse.

Mechanical Penthouse

  • Concrete pour area 2 scheduled for 4/27/21.

  • Concrete pour area 3 scheduled for 5/1/21.

Site

  • Installation of equipment continues.


55 views0 comments