Construction Update - 3/19/2021




The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (3/15/21 to 3/20/21) scheduled work activities:

G2

  • Overhead MEP work continues.

  • Layout of walls continues with installation of top tracks.

  • Exterior wall shielding at Cyclotron installation Continues.

G1

  • Overhead MEP Rough-In continues.

  • Layout of walls continues with installation of top tracks.

  • Poured walls for ramp connecting loading dock areas of HSRB – I & II

  • Catwalk installation underway

Level 1

  • Exterior Sheathing underway at SW corner of building.

  • Overhead MEP installation underway North Tower.

  • Priority wall installation underway North Tower.

Level 2

  • Installation of steel for Center bridges at levels 2, 3, & 4 is underway

Level 3

  • Shoring timbers remain in place.

Level 4

  • Shoring timbers remain in place.

Level 5

  • Pouring of columns on level 5 area 3 &4.

Level 6

  • Concrete formwork ready for concrete pour area 1 on Monday, 3/22/21 rescheduled due to storms this week.

  • Concrete forms ready in areas 6-2 as well.

  • Formwork installation continues in areas 6-3 & 6-4.

Site

  • Andrews Circle grading work/road prep continues. Base coat of asphalt will be poured on Sunday 3/21/21.

  • Pulling of electrical feeders in micro-grid vault continues.

  • Work on exterior mock up continues .

  • Work on Generator yard retaining wall continues.

Next week's (3/22/21 to 3/27/21) scheduled work activities:


G2 & G1

  • Framing of priority walls at catwalk continue.

  • Pour concrete ramp at loading docks connecting HSRB – I & II.

  • Installation of fire caulking around MEP penetrations continue.

  • Frame, hang, and finish priority wall.

Level 1

  • Overhead MEP rough-in North Tower.

  • Exterior Sheathing continues.

  • Priority Wall rough in on North Tower.

  • Installation of anchoring & Horizontal frames for curtain wall begins.

Level 2

  • Begin removal of reshoring timbers on level 2 continues.

  • Frame priority walls level 2 NE & NW South Tower.

Level 3

  • Shoring timbers remains in place.

Level 4

  • West Bridge Installation underway.

  • Steel detailing on center bridge work continues.

Level 5

  • Shoring timbers remains in place.

Level 6

  • Placement and setting of Columns Level 6 area .

  • Installation of form work for Level 6 concrete continues in area 4.

  • Installation of rebar steel in area 6-3 continues.

  • Concrete pour in area 6-1 scheduled for Monday 3/22/21, rescheduled due to storms on 3/17 & 3/18.

  • Concrete pour in area 6-2 scheduled for this week as well.

Site

  • Installation of asphalt base course on Andrews Circle scheduled for Sunday 3/21/21.

  • Work at Micro-grid vault continues.