Construction Update - 2/7/2020

This past week's (2/3/20 to 2/8/20) scheduled work activities:

  • Deep excavation continues at the G2 Level of building.

  • Demolition of 60” metal pipe under loading dock entrance and installation 24” concrete pipe in same area.

  • Excavation for retaining wall at NW Corner of jobsite, start of form work and pouring of foundations for wall.

  • Successful rock removal on Monday & Tuesday, with additional blast scheduled for Friday @ 4:30 PM

Next week's (2/10/20 to 2/15/20) scheduled work activities:


  • Deep excavation to continue at the G2 Level of building.

  • Rock removal/blasting to continue @ G1 level on Mon, 2/10, Wed, 2/12, & Fri, 2/14.

  • Form and pouring of retaining wall to continue at NW Corner of Site.

Long-term look ahead activities:


  • Potholing in Haygood drive for new sanitary line installation beginning on or about 2/24/20.

  • Erection of project tower crane on weekend of 3/14/20 - 3/15/20.




26 views0 comments