Construction Update - 1/29/21

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the team feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week’s (1/25/21 to 1/30/21) scheduled work activities:


G2

  • Overhead MEP Work, Installing Hangers continues.

G1

  • Overhead MEP Rough-In Continues.

  • Electrical Switchgear Installation.

Level 1

  • Removal of reshores at Level 1 Pour 1.

Level 3

  • Column Installation from Levels 3 to 4 Continues.

  • Level 3 pour #2 Completed.

Level 4

  • Framing and Decking installed for Level 4 Pour 2 & 3.

Site

  • Poured Retaining Wall #2.

  • Micro Grid Vault Lid poured.

  • Work on exterior mock up continues .

  • Installation for Electrical duct bank from Microgrid to building continues.

Next week’s (2/01/21 to 2/06/21) scheduled work activities:


G1

  • Overhead MEP Rough-In Continues.

  • Removal of reshores should be completed.

Level 1

  • Removal of reshores at Level 1 Pour 2.

Level 2

  • Removal of reshores at Level 2 Pour 1.

Level 3

  • Column Installation from Levels 3 to 4 Continues.

  • Concrete Pour 3 Complete.

  • Installation of forms and rebar for Level 3 pour 4 completes.

Level 4

  • Framing for Decking Level 4 Pours 2 and 3 work continues.

  • Electrical in-slab conduit rough- in continues.

Site

  • D-Line Storm line work continues.