Construction Update - 2/5/21



The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the team feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week’s (2/01/21 to 2/06/21) scheduled work activities:


G2

  • Overhead MEP Work, Installing Hangers continues.

  • Installation of Cyclotron vault door

G1

  • Overhead MEP Rough-In Continues.

  • Installation of CMU walls and wall layout continues

Level 1

  • Removal of reshores at Level 1 Pour 2.

Level 3

  • Column Installation from Levels 3 to 4 Continues.

Level 4

  • Electrical in slab rough in continues.

  • Framing and Decking installed for Level 4 Pour 2 & 3.

  • Concrete pour on Level 4 area 1 scheduled to be completed on 2/5/21.

Site

  • Poured Retaining Wall #2.

  • Installation of Grease trap.

  • Work on exterior mock up continues .

  • Installation for Electrical duct bank from Microgrid to building continues.

Next week’s (2/08/21 to 2/13/21) scheduled work activities:


G2

  • Overhead MEP rough-in continues

  • Layout of interior walls continues.

G1

  • Overhead MEP Rough-In Continues.

  • Layout of interior walls continues

Level 1

  • Removal of reshores at Level 1 Pour 3.

Level 3

  • Column Installation from Levels 3 to 4 Continues.

  • Concrete Pour for level 4 areas 2 & 3 scheduled.

Level 4

  • Framing for columns level 4 to 5 begins.

  • Electrical in-slab conduit rough- in continues.

Level 5

  • Forming of decking for Level 5 areas 1 & 2 underway.

Site

  • D-Line Storm line work continues.