Construction Update - 2/26/2021


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the team feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week's (2/22/21 to 2/27/21) scheduled work activities:


G2

  • Overhead MEP work continues.

  • Layout of walls continues with installation of top tracks.

  • Framing of Stairwell wall for stairs from G2 to G1

G1

  • Overhead MEP Rough-In Continues.

  • Layout of walls continues with installation of top tracks

Level 1

  • Removal of reshoring’s mostly complete on Level 1

Level 2

  • Readying area for removal of shoring supporting level 3 slab.

Level 3

  • Shoring remains in place.

Level 4

  • Concrete pour for Level 4 area 4 completed on Saturday, 2/20/2021.

Level 5

  • Concrete Pour completed Level 5 area 1 on Wednesday, 2/24/21.

  • Concrete pour Level 5 area 2 scheduled for Saturday, 2/27/21.

  • Form work and rebar installation underway on level 5 areas 2, 3, & 4.

  • Installing sleeves and insects in areas 5-2, & 5-3.

Site

  • Start of Andrews Circle grading work/road prep is underway.

  • Work on exterior mock up continues .

  • Forming and rebar installation underway on Plaza retaining wall for driveway down to HSRB I & II loading docks.

Next week's (3/1/21 to 3/6/21) scheduled work activities:


G2 & G1

  • Overhead MEP rough-in continues

  • Layout of interior walls continues.

  • Begin installation of fire caulking at some locations.

  • Pouring housekeeping pads for AHU (Air Handling Units)

Level 1

  • Overhead MEP rough-in continues

  • Layout of interior walls continues.

Level 2

  • Begin removal of reshoring on level 2

Level 3

  • Shoring in place

Level 4

  • Shoring in place

Level 5

  • Forming of columns to support Level 6 slab in area 5-1.

  • Continue forming and pour of additional columns to support level 6 slab in areas 6-2, 6-3, & 6-4.

Site

  • Continue forming and rebar installation retaining wall #2

  • Continue grading work on begin Andrews Circle curb and gutter on North edge (near CSX tracks) and asphalt base installation towards end of week (weather permitting).