This past week's (2/10/20 to 2/15/20) scheduled work activities:


  • Rock blasts on Monday, Wednesday, and Friday numbers 13, 14, & 15.

  • Installation of Storm Line B continues near HSRB – I loading dock entrance.

  • Forming for pour of retaining wall and installation of footings for same wall.

  • Removal of 2 pine trees per revised tree removal plan approved by City of Atlanta.

Next week's (2/17/20 to 2/22/20) scheduled work activities:


  • Rock removal scheduled for Monday, Wednesday & Friday of next week.

  • Deep excavation at the west end of building for G-2 level continues.

  • Begin pouring of site retaining wall.

  • Installation of B line storm system scheduled to be completed.

  • Installation of rerouted fire water line to begin near HSRB – I loading dock.

Long term look ahead activities:


  • Potholing in Haygood drive for new sanitary line installation beginning on or about 3/2/20 to 3/6/20.