This past week's (2/10/20 to 2/15/20) scheduled work activities:
Rock blasts on Monday, Wednesday, and Friday numbers 13, 14, & 15.
Installation of Storm Line B continues near HSRB – I loading dock entrance.
Forming for pour of retaining wall and installation of footings for same wall.
Removal of 2 pine trees per revised tree removal plan approved by City of Atlanta.
Next week's (2/17/20 to 2/22/20) scheduled work activities:
Rock removal scheduled for Monday, Wednesday & Friday of next week.
Deep excavation at the west end of building for G-2 level continues.
Begin pouring of site retaining wall.
Installation of B line storm system scheduled to be completed.
Installation of rerouted fire water line to begin near HSRB – I loading dock.
Long term look ahead activities:
Potholing in Haygood drive for new sanitary line installation beginning on or about 3/2/20 to 3/6/20.
Erection of project tower crane on weekend of 3/14/20 - 3/15/20.