Construction Update - 12/10/21


This past week's (12/06/21 to 12/11/21) scheduled work activities:

G2

  • Installation of plumbing fixtures.

  • Radiotracer and Hotcell installation continues.

G1

  • BSL North – In Wall Inspections.

  • Closing in and finishing walls – BSL – South.

  • Leveling of floors in 3T MRI room completed.

  • Installation of Stonhard in North vivarium area continues.

  • Framing of Wonder Wall in G1 Lobby is underway.

Level 1

  • Hanging and finishing drywall – South Tower.

Level 2

  • Lab lighting and service panel installations- South Tower.

  • Hanging and Finishing drywall – South Tower.

  • Installation of plumbing fixtures in community restrooms completed.

Level 3

  • Installation of office & corridor lighting fixtures.

  • Installation of Lab lighting and service panels.

  • Installation of fireproofing on East connector bridges in underway on L2& L2

Level 4

  • North Offices & Corridor lighting installation continues.

  • Tile installation in community restrooms is underway.

Level 5

  • Hanging walls and ceilings in lab neighborhoods underway.

  • Finishing off drywall walls and ceiling in community restrooms continues.

Level 6

  • Installation of “eyebrow” steel on exterior level 6 continues.

  • Installation of Steel decking on eyebrow continues.

  • Non-priority wall framing continues at South tower.

Mechanical Penthouse

  • MEP Installation continues in South & North towers.

  • Installation of cooling towers piping continues.

  • Exterior framing & sheathing continues on South tower.

  • Air and water barrier installation continues on exterior walls North & South Towers.

  • Installation of Metal Framing and sheathing on skylight continues.

  • caulking of skylight glass has begun.

Skin:

  • Marble installation and caulking on Northwest Façades continues.

  • Marble installation and caulking continues on the West Façade .

  • Installation of marble on MC #6 continues at SW corner.

  • Granite installation on Northwest Façade continues.

  • Glazing Installation in G-1 lobby area is 100% complete.

  • Installation of TPO roofing on Penthouse roofs continue.

  • Installation of the CMU walls of the East Stair tower continues.

  • Installation of framing for curtain wall #1 has begun.

HSRB – I Vivarium Expansion:

  • Installation of Metal deck roof on vivarium expansion is underway.


Next week's (12/13/21 to 12/18/21) scheduled work activities:

G2

  • Installation of radiotracer hot cells continues.

  • GE Cyclotron mobilize materials.

  • Hamilton Biorepository remobilize & begin installation.

  • H2I remobilize to complete installation.

G1

  • Closing in and finishing walls – BSL South.

  • Continue framing for wonder wall in lobby area.

  • Inspections in imaging area and closing of walls.

  • Vivarium Stonhard installation continues.

Level 1

  • Hanging remaining drywall in North tower.

  • Hanging and finishing drywall walls and ceilings- South tower.

Level 2

  • Installation of lab lighting and service panels in South Tower continues.

  • Hanging and finishing walls – South.

  • Primer coat & first coat of color paint - South.

Level 3

  • Installation of office and corridor lighting.

  • Installation of lab lighting and Service panels.

  • Wall Inspections – Southwest.

Level 4

  • Installation of lighting in corridors & offices in North Tower continues.

  • Installation of plumbing fixtures in community restrooms.

  • Fireproofing of East connector bridges continues.

Level 5

  • Installation of fan coil units.

Level 6:

  • Installation of eyebrow steel continues.

  • Non-priority wall framing continues – South Tower.

  • Installation of metal deck on top of eyebrow continues.

  • Fireproofing of interior of eyebrow continues.

Mechanical Penthouse

  • Installation of overhead MEP Continues – North & South Towers

  • Hanging of walls North & South.

  • Continue framing and sheathing of Skylight walls.

  • Work on Installation of Skylight glass (caulking) continues this week.

Skin

  • Air and Water Barrier installation continues South tower.

  • Punched window openings aluminum surrounds installation continues on South elevation.

  • Marble installation continues on Northwest & Northeast Façade.

  • Marble installation continues on MC # 6, 7 & 8 (master climber)

  • Installation of TPO roofing continues on South Penthouse Roof.

HSRB – I Vivarium Expansion:

  • Pouring of concrete deck on top of metal decking.



65 views0 comments