This past week's (12/06/21 to 12/11/21) scheduled work activities:
G2
Installation of plumbing fixtures.
Radiotracer and Hotcell installation continues.
G1
BSL North – In Wall Inspections.
Closing in and finishing walls – BSL – South.
Leveling of floors in 3T MRI room completed.
Installation of Stonhard in North vivarium area continues.
Framing of Wonder Wall in G1 Lobby is underway.
Level 1
Hanging and finishing drywall – South Tower.
Level 2
Lab lighting and service panel installations- South Tower.
Hanging and Finishing drywall – South Tower.
Installation of plumbing fixtures in community restrooms completed.
Level 3
Installation of office & corridor lighting fixtures.
Installation of Lab lighting and service panels.
Installation of fireproofing on East connector bridges in underway on L2& L2
Level 4
North Offices & Corridor lighting installation continues.
Tile installation in community restrooms is underway.
Level 5
Hanging walls and ceilings in lab neighborhoods underway.
Finishing off drywall walls and ceiling in community restrooms continues.
Level 6
Installation of “eyebrow” steel on exterior level 6 continues.
Installation of Steel decking on eyebrow continues.
Non-priority wall framing continues at South tower.
Mechanical Penthouse
MEP Installation continues in South & North towers.
Installation of cooling towers piping continues.
Exterior framing & sheathing continues on South tower.
Air and water barrier installation continues on exterior walls North & South Towers.
Installation of Metal Framing and sheathing on skylight continues.
caulking of skylight glass has begun.
Skin:
Marble installation and caulking on Northwest Façades continues.
Marble installation and caulking continues on the West Façade .
Installation of marble on MC #6 continues at SW corner.
Granite installation on Northwest Façade continues.
Glazing Installation in G-1 lobby area is 100% complete.
Installation of TPO roofing on Penthouse roofs continue.
Installation of the CMU walls of the East Stair tower continues.
Installation of framing for curtain wall #1 has begun.
HSRB – I Vivarium Expansion:
Installation of Metal deck roof on vivarium expansion is underway.
Next week's (12/13/21 to 12/18/21) scheduled work activities:
G2
Installation of radiotracer hot cells continues.
GE Cyclotron mobilize materials.
Hamilton Biorepository remobilize & begin installation.
H2I remobilize to complete installation.
G1
Closing in and finishing walls – BSL South.
Continue framing for wonder wall in lobby area.
Inspections in imaging area and closing of walls.
Vivarium Stonhard installation continues.
Level 1
Hanging remaining drywall in North tower.
Hanging and finishing drywall walls and ceilings- South tower.
Level 2
Installation of lab lighting and service panels in South Tower continues.
Hanging and finishing walls – South.
Primer coat & first coat of color paint - South.
Level 3
Installation of office and corridor lighting.
Installation of lab lighting and Service panels.
Wall Inspections – Southwest.
Level 4
Installation of lighting in corridors & offices in North Tower continues.
Installation of plumbing fixtures in community restrooms.
Fireproofing of East connector bridges continues.
Level 5
Installation of fan coil units.
Level 6:
Installation of eyebrow steel continues.
Non-priority wall framing continues – South Tower.
Installation of metal deck on top of eyebrow continues.
Fireproofing of interior of eyebrow continues.
Mechanical Penthouse
Installation of overhead MEP Continues – North & South Towers
Hanging of walls North & South.
Continue framing and sheathing of Skylight walls.
Work on Installation of Skylight glass (caulking) continues this week.
Skin
Air and Water Barrier installation continues South tower.
Punched window openings aluminum surrounds installation continues on South elevation.
Marble installation continues on Northwest & Northeast Façade.
Marble installation continues on MC # 6, 7 & 8 (master climber)
Installation of TPO roofing continues on South Penthouse Roof.
HSRB – I Vivarium Expansion:
Pouring of concrete deck on top of metal decking.
Comments