The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as managements feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice. The Job Site will be closed (12/25 to 12/27) and (1/1/21 to 1/3/21). As a result of the shortened work weeks and Emory’s winter break period this will be the last weekly report until the report on 1/8/2021.
This past week's (12/14/20 to 12/19/20) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In Continues
G1
Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.
Installation of CMU (concrete masonry units) was underway.
Formwork Removal under pour #8 underway.
Level 1
All level #1 concrete pours are complete!
Installation of Level 1 to Level 2 columns continues.
Installation of Level 1 plaza root stop and drainage mat.
Level 2
Site
Erection of steel for mock ups begins.
Installation of generator vault began.
Installation of retaining wall #2 footings began.
Next week's (12/21/20 to 12/26/20) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In continues.
G1
CMU (concrete masonry units) wall installation continues
Electrical and Plumbing Overhead Rough-In continues in Main electrical room.
Level 1
Removing form work for concrete pour Level 1 pour #9.
Level 2
Site Work
Generator yard vault installation continues.
Retaining Wall 2 Footing Installation continues.