Construction Update - 12/13/19
This past week's (12/9 – 12/14) scheduled work activities.
Ground Breaking Ceremony held on 12/11/19
Storm Line A is nearing completion, last section to tie into HSRB – I line in area under Brumley Bridge.
Excavation for Storm line B alone Andrews Circle has begun.
Compacting of soil over previously installed section of storm line A.
Next week's (12/16 – 12/21) scheduled activities.
Finish installation/tie in of Storm Line A. weather permitting.
Continue work on storm line B.
Continue work on storm line C.
The job site will be closed on the following days for the holidays:
12/24/19
12/25/19
12/31/19
1/1/20