The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (11/30 to 12/04/20) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In Continues
G1
Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.
Installation of CMU (concrete masonry units) walls has begun.
Level 1
Level 2
Vivarium Expansion
Installation of below slab waterproofing for new slab on grade in vivarium.
Next week's (12/07/20 to 12/12/20) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In continues.
G1
CMU (concrete masonry units) wall installation.
Electrical and Plumbing Overhead Rough-In continues.
Level 1
Level 2
Installing formwork and rebar for Level 2 pour #1