top of page
  • Writer's pictureemoryhsrb2

Construction Update - 11/20/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.


This past week's (11/16/20 to 11/21/20) scheduled work activities:


G2

  • Electrical and Plumbing Overhead Rough-In Continues

G1

  • Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.

Level 1

  • Level 1 pour # 5 completed.

  • Level 1 pour #7 completed.

  • Installing Formwork for Pour 9

  • Installing Plaza Waterproofing onto pour #3 area.

Level 2

  • Installing formwork for level 2 pour #1.

  • Installation of backfill around g-2 foundation wall.

Vivarium Expansion

  • Foundation Wall poured.

Next week's (11/23/20 to 11/25/20) scheduled work activities:


(Job site will be closed on 11/26 & 11/27 for Thanksgiving holiday)

G2

  • Electrical and Plumbing Overhead Rough-In continues.

G1

  • Electrical and Plumbing Overhead Rough-In continues.

Level 1

  • Removing formwork for Level 1 pour 5 & pour 7

  • Installing rebar for pour 8.

  • Installation of hot applied waterproofing on level 1 pour #5.

Level 2

  • Installing formwork and columns for level 2 pour 1

Vivarium Expansion

  • installation of waterproofing for vivarium slab on grade.



15 views0 comments

Recent Posts

See All

Comments


bottom of page