The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (10/5/20 to 10/10/20) scheduled work activities:
G2:
Continuing Backfilling G2 Foundation Walls
G1:
Excavating for additional North Retaining Wall work.
Removal of forms on recently poured section of North retaining wall
Reinforcing for Slab on Grade Pour 4 West
Pouring Slab on Grade Pour 4 West
Waterproofing and Rebar for Slab on Grade Pour 2
Level 1:
Level 1, Pour #4 poured.
Installing Reinforcing on Level 1 Pour 3
Formwork Installation for Level 1 Pour 5
Vivarium Expansion:
Continue Installing Vivarium Foundation System
Continue MEP Installation in Vivarium Expansion
Next week's (10/12/20 to 10/17/20) scheduled work activities:
Site:
Pour North retaining wall footing.
G2:
Continuing backfilling G2 foundation walls.
G1:
Continue Foundation Wall Installation.
Pour Slab on Grade pour #2
Level 1:
Vivarium Expansion:
Continue Installing Vivarium Foundation System.
Comments