top of page
  • Writer's pictureemoryhsrb2

Construction Update - 10/9/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (10/5/20 to 10/10/20) scheduled work activities:


G2:

  • Continuing Backfilling G2 Foundation Walls

G1:

  • Excavating for additional North Retaining Wall work.

  • Removal of forms on recently poured section of North retaining wall

  • Reinforcing for Slab on Grade Pour 4 West

  • Pouring Slab on Grade Pour 4 West

  • Waterproofing and Rebar for Slab on Grade Pour 2

Level 1:

  • Level 1, Pour #4 poured.

  • Installing Reinforcing on Level 1 Pour 3

  • Formwork Installation for Level 1 Pour 5

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System

  • Continue MEP Installation in Vivarium Expansion

Next week's (10/12/20 to 10/17/20) scheduled work activities:

Site:

  • Pour North retaining wall footing.

G2:

  • Continuing backfilling G2 foundation walls.

G1:

  • Continue Foundation Wall Installation.

  • Pour Slab on Grade pour #2

Level 1:

  • Installing formwork for Level 1, pour #5

  • Pouring Level 1, pour #3

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System.


19 views0 comments

Recent Posts

See All
bottom of page