Construction Update - 10/30/2020

Updated: Nov 6, 2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (10/26/20 to 10/31/20) scheduled work activities:

G2:

  • Continuing backfilling G2 foundation walls.

G1:

  • Continue Foundation Wall Installation.

  • G1 to L1 Column Installation

Level 1:

  • Installing formwork for Level 1, pour 7

  • Installing rebar for level 1, Pour 8.

  • Pouring Level 1, pour 5.

  • Pouring Level 1, pour 6.

  • MEP Rough in on Level 1 pour 6.

  • Backfill plaza deck.

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System.

Next week's (11/02/20 to 11/07/20) scheduled work activities:

G2:

  • Electrical and Plumbing Overhead Rough-In

  • Backfill Continues around G2.

G1:

  • Finishes Level 1 Foundation Wall Installation

  • Electrical and Plumbing Overhead Rough-In Begins

Level 1:

  • Installing Formwork for Level 1 Pour 6 and 7

  • Finalized Reinforcement for Pour 2

  • Installing Reinforcing for Pour 5

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System



45 views0 comments