Construction Update - 10/23/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (10/19/20 to 10/24/20) scheduled work activities:

G2:

  • Continuing Backfilling G2 Foundation Walls

G1:

  • Continuing Foundation Wall Installation

Level 1:

  • Installing Formwork for Level 1 Pour 6.

  • Installation of rebar for Level 1 Pour 5.

  • Pouring level 1 pour 2.

  • MEP duct bank (utilidor) Installation

  • MEP rough in on level 1 pour 5.

  • Prepare Plaza Deck for backfill.

  • Level 1, pour 3 form work removed.

  • Level 1 pour 4 formwork removed.

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System

Next week's (10/26/20 to 10/31/20) scheduled work activities:

G2:

  • Continuing backfilling G2 foundation walls.

G1:

  • Continue Foundation Wall Installation.

Level 1:

  • Installing formwork for Level 1, pour 7

  • Installing rebar for level 1, Pour 8.

  • Pouring Level 1, pour 5.

  • Pouring Level 1, pour 6.

  • MEP Rough in on Level 1 pour 6.

  • Backfill plaza deck.

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System.