top of page
  • Writer's pictureemoryhsrb2

Construction Update - 10/22/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Effective Monday, August 9, 2021 Je Dunn will reinstitute/require the wearing of face masks on the job site. Additional new policy may be added in the future.

This past week's (10/18/21 to 10/23/21) scheduled work activities:

G2

  • Radio-pharmacy Hot cells installation is Continues

  • Opening in the Cyclotron vault wall has been filled in with concrete.Overhead rough-in continues

G1

  • Vivarium North wall and ceiling final inspections before cover up.

  • Wall framing in G1 BSL - North area continues.

  • Wall and ceiling cover up & finishing is underway in Vivarium -South

  • In wall & ceiling rough – in continues in BSL- South area.

  • Stonehard Installation started Vivarium South.

  • Installation of Elevator 4 started.

Level 1

  • Lab Neighborhood wall & ceiling cover up underway.

  • Single restroom hard ceiling cover up underway in North Tower.

  • Tile and Counter top installation has begun in Community restrooms

Level 2

  • Erection of steel for East connector bridges continues. Community restroom wall & ceiling cover ups are underway.

Level 3

  • Lab Neighborhood wall inspections

  • Community restroom wall and ceiling inspections.

Level 4

  • Lighting Rough-in in North Tower continues.

  • Community restroom hard ceiling rough -ins underway.

Level 5

  • One siding of drywall in North & South Towers continues.

Level 6

  • Overhead MEP installation continues.

  • Phoenix valve installation is underway.

  • Installation of “eyebrow” steel on exterior level 6 continues.

Mechanical Penthouse

  • MEP Installation continues in South & North towers.

  • Installation of vapor barrier roofing layer on North Tower Mechanical roof is underway.

  • Exterior framing & sheathing continues on South tower parapet wall.

  • Exterior framing & sheathing continues on South tower mechanical penthouse roof parapet wall.

  • Air and water barrier installation continues on exterior walls North & South Towers.

  • Fireproofing of skylight structural steel has begun.

  • Installation of 3 cooling towers was completed on South Tower on Tuesday & Wednesday.

Skin:

  • Marble installation and caulking on Northeast & Northwest Façades continues.

  • Installation of windows in punched openings on South Façade continues.

  • Granite installation on Northwest Façade continues.

  • Glazing Installation in G-1 lobby area has begun.

  • Curtain wall #4 was completed.

HSRB – I Vivarium Expansion:

  • Erection of steel columns and beams continues.

Next week's (10/25/21 to 10/30/21) scheduled work activities:

G2

  • Installation of Cyclotron continues.

  • Installation of radio-pharmacy Hot cells continues.

  • Overhead Rough-in continues.

  • H2I Mobilization and lab casework installation begins on G-2.

G1

  • Vivarium – North wall and ceiling framing inspection s continue.

  • In wall and overhead rough-in BSL- North &South.

  • Stonhard installation underway in vivarium – South area.

  • Installation of Elevator #4 continues.

  • Startup of Temporary HVAC for temporary air.

Level 1

  • Office & corridor lighting installation underway.

  • Tile installation in showers underway.

  • Wall cover up inspections – North Offices.

Level 2

  • Lab Neighborhood wall & hard ceiling cover ups – North Tower.

  • Community restroom wall & hard ceiling cover ups completed.

Level 3

  • Lab Neighborhood hard ceiling inspections.

  • MEP rough -ins at bridges.

  • Hanging and finishing drywall – North Offices.

Level 4

  • Community Restroom hard ceiling inspections.

  • Lighting Rough - in at hard ceilings South Tower.

  • Hanging and finishing or drywall North Offices.

Level 5

  • One siding of drywall – North & South Towers continues.

  • Community restroom hard ceiling rough – in underway.

Level 6

  • Overhead MEP installation continues.

  • Installation of Phoenix valves continue.

  • Installation of eyebrow Steel continues.

  • Fireproofing of eyebrow steel underway.

Mechanical Penthouse

  • Installation of overhead MEP Continues – North & South Towers

  • Exterior framing and sheathing of South penthouse continues.

  • Air & water barrier installation on exterior sheathing of North Tower continues

  • Framing of plywood band for skylight.

  • Installation of fireproofing on skylight steel.

  • Complete fire-proofing of South Penthouse beams and columns.

  • Installation of vapor barrier on South Tower Mechanical Penthouse roof will begin.

Skin

  • Air and Water Barrier installation continues.

  • Punched window openings aluminum surrounds installation continues on East elevation.

  • Marble installation continues on Northwest & Northeast Façade.

  • Marble installation will begin on MC # 6 (master climber)

  • Installation of fire rated frames on L-1.

  • Complete Curtain Wall #4.

HSRB – I Vivarium Expansion:

  • Continue installation of steel beams & Columns.



4 views0 comments

Recent Posts

See All
bottom of page