Construction Update - 10/2/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (9/28/20 to 10/3/20) scheduled work activities:


G2:

  • Backfilling of G2 Continuous Foundation Walls Continues

G1:

  • Installation of North and South Foundation Walls Continues

  • Stone Fill for Slab on Grade Pour 4 West

  • Slab on Grade Pour 2 Underground MEP Installation Continues

  • Waterproofing for Slab on Grade Pour 4 West

Level 1:

  • Forming Level 1 Pour 3 Starts

  • Reinforcing for Level 1 Pour 4 Continues

Vivarium Expansion:

  • MEP Installation in Vivarium Expansion

  • Continue Installing Vivarium Foundation System

Next week's (10/5/20 to 10/10/20) scheduled work activities:


G2:

  • Continuing Backfilling G2 Foundation Walls

G1:

  • Excavating for North Retaining Wall

  • Pouring Slab on Grade Pour 4 West

  • Waterproofing Slab on Grade Pour 2

  • Reinforcing for Slab on Grade Pour 4 West

Level 1:

  • Installing Reinforcing on Level 1 Pour 3

  • Formwork Installation for Level 1 Pour 5

Vivarium Expansion:

  • Continue Installing Vivarium Foundation System

  • Continue MEP Installation in Vivarium Expansion


8 views0 comments