The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (9/28/20 to 10/3/20) scheduled work activities:
G2:
Backfilling of G2 Continuous Foundation Walls Continues
G1:
Installation of North and South Foundation Walls Continues
Stone Fill for Slab on Grade Pour 4 West
Slab on Grade Pour 2 Underground MEP Installation Continues
Waterproofing for Slab on Grade Pour 4 West
Level 1:
Forming Level 1 Pour 3 Starts
Reinforcing for Level 1 Pour 4 Continues
Vivarium Expansion:
MEP Installation in Vivarium Expansion
Continue Installing Vivarium Foundation System
Next week's (10/5/20 to 10/10/20) scheduled work activities:
G2:
Continuing Backfilling G2 Foundation Walls
G1:
Excavating for North Retaining Wall
Pouring Slab on Grade Pour 4 West
Waterproofing Slab on Grade Pour 2
Reinforcing for Slab on Grade Pour 4 West
Level 1:
Installing Reinforcing on Level 1 Pour 3
Formwork Installation for Level 1 Pour 5
Vivarium Expansion:
Continue Installing Vivarium Foundation System
Continue MEP Installation in Vivarium Expansion