The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as managements feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.
This past week's (1/4/21 to 1/9/21) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In Continues
G1
Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.
Installation of CMU (concrete masonry units) was underway.
Level 1
Installation of Level 1 plaza root stop and water proofing continues.
Level 2
Level 3
Installation of Columns from Level 2 to Level 3 continues.
Elevated slab formwork for installation of rebar for Level 3 slab is underway.
Site
Erection of steel for mock ups continues.
Installation of generator vault continues.
Installation of retaining wall #2 footings and continuation of conduits to generator yard is proceeding.
Rerouting of North storm line continues.
HSRB-I Vivarium Expansion
Concrete slab on grade was poured on 1/6/21.
Next week's (1/11/21 to 1/16/21) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In continues.
Removal of reshoring begins.
G1
CMU (concrete masonry units) wall installation continues
Electrical and Plumbing Overhead Rough-In continues in Main electrical room.
Level 2
Level 3 concrete #1 schedule for this week.
Installation of columns from level 2 to level 3 will continue.
Level 3
Level 3 concrete pour #1 scheduled.
Formwork and rebar installation for Level 3 elevated deck continues.
In slab electrical conduit continues in Level 3 elevated deck.
Site Work
Generator yard vault installation continues.
Grease trap delivery and installation begins.
Retaining Wall 2 Footing Installation continues.
Rerouting of North storm line continues.