Construction Update - 1/8/2021


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as managements feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.

This past week's (1/4/21 to 1/9/21) scheduled work activities:


G2

  • Electrical and Plumbing Overhead Rough-In Continues

G1

  • Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.

  • Installation of CMU (concrete masonry units) was underway.

Level 1

  • Installation of Level 1 plaza root stop and water proofing continues.

Level 2

  • Level 2 concrete pour #3 was completed.

  • Installation of formwork for concrete pour #4 continues.

  • In slab installation of electrical conduit continues Pour #4 area.

  • Level 2 concrete pour #4 scheduled for Saturday Morning 1/9/21.

Level 3

  • Installation of Columns from Level 2 to Level 3 continues.

  • Elevated slab formwork for installation of rebar for Level 3 slab is underway.

Site

  • Erection of steel for mock ups continues.

  • Installation of generator vault continues.

  • Installation of retaining wall #2 footings and continuation of conduits to generator yard is proceeding.

  • Rerouting of North storm line continues.

HSRB-I Vivarium Expansion

  • Concrete slab on grade was poured on 1/6/21.

Next week's (1/11/21 to 1/16/21) scheduled work activities:

G2

  • Electrical and Plumbing Overhead Rough-In continues.

  • Removal of reshoring begins.

G1

  • CMU (concrete masonry units) wall installation continues

  • Electrical and Plumbing Overhead Rough-In continues in Main electrical room.

Level 2

  • Level 3 concrete #1 schedule for this week.

  • Installation of columns from level 2 to level 3 will continue.

Level 3

  • Level 3 concrete pour #1 scheduled.

  • Formwork and rebar installation for Level 3 elevated deck continues.

  • In slab electrical conduit continues in Level 3 elevated deck.

Site Work

  • Generator yard vault installation continues.

  • Grease trap delivery and installation begins.

  • Retaining Wall 2 Footing Installation continues.

  • Rerouting of North storm line continues.



41 views0 comments