Construction Update - 1/25/21

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week's (1/18/21 to 1/23/21) scheduled work activities:


G2

  • Overhead MEP Work, Installing Hangers.

  • Removal of reshores at Level G2 Pours 2 and 3.

G1

  • Overhead MEP Rough-In Continues.

  • CMU Installation Complete.

  • Paint Complete in MEP / Priority Rooms.

Level 1

  • Removal of reshores at Level 1 Pour 1.

Level 2

  • Formwork Removal and Installation of reshores.

Level 3

  • Column Installation from Levels 3 to 4 Continues.

  • Level 3 pour #2 & #3 rebar and formwork completed.

  • Concrete Pour 2 Completed on Saturday 1/23/21.

Next week's (1/25/21 to 1/30/21) scheduled work activities:


G1

  • Overhead MEP Rough-In Continues.

Level 1

  • Removal of reshores at Level 1 Pour 2.

Level 2

  • Removal of reshores at Level 2 Pour 1.

Level 3

  • Column Installation from Levels 3 to 4 Continues.

  • Concrete Pour 3 Complete.

Level 4

  • Framing and Decking Level 4 Pours 2 and 3.

Site

  • Pouring Retaining Wall 2.