The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as managements feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.
This past week's (1/11/21 to 1/16/21) scheduled work activities:
G2
Electrical and Plumbing Overhead Rough-In Continues
G1
Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.
Installation of CMU (concrete masonry units) underway, and painting where follows.
Delivery of Chillers # 1 & #2
Level 1
Cellular Concrete installation on Plaza deck began.
Level 2
Level 2 form work removal and reshore installation continues.
Level 3
Site
Grease Trap delivery and installation began.
Installation of generator vault continues.
HSRB-I Vivarium Expansion
Concrete slab on grade was poured on 1/6/21.
Next week's (1/18/21 to 1/23/21) scheduled work activities.
The Jobsite will be open on 1/18/2021
G2
Electrical and Plumbing Overhead Rough-In continues.
Removal of reshoring begins.
G1
CMU (concrete masonry units) wall installation continues
Electrical and Plumbing Overhead Rough-In continues in Main electrical room.
Level 1
Installation of Cellular concrete on plaza deck to finish.
Level 2
Form work removal and reshore installation to continue.
Level 3
Site Work
Generator yard vault installation continues.
Grease trap delivery and installation continues.
Retaining Wall 2 Footing Installation continues.
Comments