top of page
  • Writer's pictureemoryhsrb2

Construction Update - 1/15/2021


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as managements feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week's (1/11/21 to 1/16/21) scheduled work activities:

G2

  • Electrical and Plumbing Overhead Rough-In Continues

G1

  • Electrical and Plumbing Overhead Rough-In Continues, in main electrical and plumbing rooms.

  • Installation of CMU (concrete masonry units) underway, and painting where follows.

  • Delivery of Chillers # 1 & #2

Level 1

  • Cellular Concrete installation on Plaza deck began.

Level 2

  • Level 2 form work removal and reshore installation continues.

Level 3

  • Concrete pour for level 3 pour #1 scheduled for Saturday 1/16/2021

  • Level 3 pour #3 formwork installation begins.

Site

  • Grease Trap delivery and installation began.

  • Installation of generator vault continues.

HSRB-I Vivarium Expansion

  • Concrete slab on grade was poured on 1/6/21.

Next week's (1/18/21 to 1/23/21) scheduled work activities.


The Jobsite will be open on 1/18/2021

G2

Electrical and Plumbing Overhead Rough-In continues.

Removal of reshoring begins.

G1

  • CMU (concrete masonry units) wall installation continues

  • Electrical and Plumbing Overhead Rough-In continues in Main electrical room.

Level 1

  • Installation of Cellular concrete on plaza deck to finish.

Level 2

Form work removal and reshore installation to continue.

Level 3

  • Level 3 Pour #2 scheduled for 1/21/2021.

  • Level 3 pour #3 Formwork install finishes and rebar installation continues.

  • Level 3 pour $4 formwork installation begins.

Site Work

  • Generator yard vault installation continues.

  • Grease trap delivery and installation continues.

  • Retaining Wall 2 Footing Installation continues.



73 views0 comments

Recent Posts

See All
bottom of page