Construction Update - 1/14/2022


The HSRB – II Jobsite will be closed on Monday 1/17/22 in observance of MLK Holiday.

This past week's (1/10/22 to 1/14/22) scheduled work activities:

G2

  • Electrical connections & install of permanent light

  • Installation of air distribution systems.

G1

  • Hanging/finishing of drywall of Drywall.

  • Vivarium fire alarm and low voltage cabling installation.

  • Continue installation of Phoenix valves at catwalk above BSL3 area.

Level 1

  • Electrical System trim out of lights and receptacles.

  • Primer and 1st coat of finish paint in North offices.

Level 2

  • Ductwork rough-in at East connector Bridges.

  • Electrical System trim outs.

  • Hanging/finishing of drywall continues.

Level 3

  • Finishing drywall in South Tower.

  • East monumental stair installation.

  • Hanging ACT grid in South Tower.

Level 4

  • Hanging drywall South Tower.

  • Electrical trim-out of ACT – South Tower.

Level 5

  • Installation of “shoes” framing for glass handrailing at West atrium.

Level 6

  • Installation of drains on eyebrows.

  • Installation of fan coil units – North Tower.

Mechanical Penthouse

  • Start up of Air handler Unit (AHU) 1.3

  • Installation of Fan Coil Units – North Tower.

  • Work on exterior of skylight continues

Skin:

  • Marble installation on West and Southwest facades.

  • Installation of TPO roofing on South Penthouse roofs continues.

  • Installation of steel framing for curtain wall #1 and stairs continues.

HSRB – I Vivarium Expansion

  • Hanging of plumbing mains underway.

Site:

  • Installation of light weight soils for plaza area is also underway.

Next week's (1/17/22 to 1/22/22) scheduled work activities:

G2

  • Installation of Stonhard floors.

G1

  • Installation of light fixtures in vivarium spaces.

  • Drywall finishing in corridors & Animal Transient rooms.

  • MEP work continues at catwalk above BSL 3 labs.

  • Framing at Wonder Wall continues.

Level 1

  • Terminate VAV’s and FCU Units.

  • Layout and framing of Granting Garden Wall.

  • Interior storefront glass installation continues.

Level 2

  • Prime & First coat of paint – North Tower.

  • Atrium soffit framing will begin.

Level 3

  • Prime & First coat of paint – South Tower.

  • Hanging Drywall – North Tower.

Level 4

  • Lab Lighting and Service panel installation.

  • Hanging Drywall in – South Tower.

Level 5

  • Begin Installation of Drywall – South Tower.

Level 6

  • Continue Installation of eyebrow drains.

  • Continue Installation of fan coil units in North Tower.

  • Installing of “shoes” for atrium hand railing.

Mechanical Penthouse

  • Eyebrow framing above Master Climbers #5 & #6.

  • Continue with electrical equipment connections and installation of receptacles.

Skin

  • Marble installation continues on MC # 7, 8 & 9 (master climber)

  • Installation of TPO roofing continues on South Penthouse Roof continues.

  • Curtin wall #1 installation of framing to continues.

HSRB – I Vivarium Expansion:

  • Installation of Overhead plumbing pipe continues.

Site:

  • Layout of Plaza deck and installation of soils continues.