The HSRB – II Jobsite will be closed on Monday 1/17/22 in observance of MLK Holiday.
This past week's (1/10/22 to 1/14/22) scheduled work activities:
G2
Electrical connections & install of permanent light
Installation of air distribution systems.
G1
Hanging/finishing of drywall of Drywall.
Vivarium fire alarm and low voltage cabling installation.
Continue installation of Phoenix valves at catwalk above BSL3 area.
Level 1
Electrical System trim out of lights and receptacles.
Primer and 1st coat of finish paint in North offices.
Level 2
Ductwork rough-in at East connector Bridges.
Electrical System trim outs.
Hanging/finishing of drywall continues.
Level 3
Finishing drywall in South Tower.
East monumental stair installation.
Hanging ACT grid in South Tower.
Level 4
Hanging drywall South Tower.
Electrical trim-out of ACT – South Tower.
Level 5
Installation of “shoes” framing for glass handrailing at West atrium.
Level 6
Installation of drains on eyebrows.
Installation of fan coil units – North Tower.
Mechanical Penthouse
Start up of Air handler Unit (AHU) 1.3
Installation of Fan Coil Units – North Tower.
Work on exterior of skylight continues
Skin:
Marble installation on West and Southwest facades.
Installation of TPO roofing on South Penthouse roofs continues.
Installation of steel framing for curtain wall #1 and stairs continues.
HSRB – I Vivarium Expansion
Hanging of plumbing mains underway.
Site:
Installation of light weight soils for plaza area is also underway.
Next week's (1/17/22 to 1/22/22) scheduled work activities:
G2
Installation of Stonhard floors.
G1
Installation of light fixtures in vivarium spaces.
Drywall finishing in corridors & Animal Transient rooms.
MEP work continues at catwalk above BSL 3 labs.
Framing at Wonder Wall continues.
Level 1
Terminate VAV’s and FCU Units.
Layout and framing of Granting Garden Wall.
Interior storefront glass installation continues.
Level 2
Prime & First coat of paint – North Tower.
Atrium soffit framing will begin.
Level 3
Prime & First coat of paint – South Tower.
Hanging Drywall – North Tower.
Level 4
Lab Lighting and Service panel installation.
Hanging Drywall in – South Tower.
Level 5
Begin Installation of Drywall – South Tower.
Level 6
Continue Installation of eyebrow drains.
Continue Installation of fan coil units in North Tower.
Installing of “shoes” for atrium hand railing.
Mechanical Penthouse
Continue with electrical equipment connections and installation of receptacles.
Skin
Marble installation continues on MC # 7, 8 & 9 (master climber)
Installation of TPO roofing continues on South Penthouse Roof continues.
Curtin wall #1 installation of framing to continues.
HSRB – I Vivarium Expansion:
Installation of Overhead plumbing pipe continues.
Site:
Layout of Plaza deck and installation of soils continues.