The HSRB – II Jobsite will be closed on Monday 1/17/22 in observance of MLK Holiday.
This past week's (1/10/22 to 1/14/22) scheduled work activities:
G2
Electrical connections & install of permanent light
Installation of air distribution systems.
G1
Hanging/finishing of drywall of Drywall.
Vivarium fire alarm and low voltage cabling installation.
Continue installation of Phoenix valves at catwalk above BSL3 area.
Level 1
Electrical System trim out of lights and receptacles.
Primer and 1st coat of finish paint in North offices.
Level 2
Ductwork rough-in at East connector Bridges.
Electrical System trim outs.
Hanging/finishing of drywall continues.
Level 3
Finishing drywall in South Tower.
East monumental stair installation.
Hanging ACT grid in South Tower.
Level 4
Hanging drywall South Tower.
Electrical trim-out of ACT – South Tower.
Level 5
Installation of “shoes” framing for glass handrailing at West atrium.
Level 6
Installation of drains on eyebrows.
Installation of fan coil units – North Tower.
Mechanical Penthouse
Start up of Air handler Unit (AHU) 1.3
Installation of Fan Coil Units – North Tower.
Work on exterior of skylight continues
Skin:
Marble installation on West and Southwest facades.
Installation of TPO roofing on South Penthouse roofs continues.
Installation of steel framing for curtain wall #1 and stairs continues.
HSRB – I Vivarium Expansion
Hanging of plumbing mains underway.
Site:
Installation of light weight soils for plaza area is also underway.
Next week's (1/17/22 to 1/22/22) scheduled work activities:
G2
Installation of Stonhard floors.
G1
Installation of light fixtures in vivarium spaces.
Drywall finishing in corridors & Animal Transient rooms.
MEP work continues at catwalk above BSL 3 labs.
Framing at Wonder Wall continues.
Level 1
Terminate VAV’s and FCU Units.
Layout and framing of Granting Garden Wall.
Interior storefront glass installation continues.
Level 2
Prime & First coat of paint – North Tower.
Atrium soffit framing will begin.
Level 3
Prime & First coat of paint – South Tower.
Hanging Drywall – North Tower.
Level 4
Lab Lighting and Service panel installation.
Hanging Drywall in – South Tower.
Level 5
Begin Installation of Drywall – South Tower.
Level 6
Continue Installation of eyebrow drains.
Continue Installation of fan coil units in North Tower.
Installing of “shoes” for atrium hand railing.
Mechanical Penthouse
Skin
Marble installation continues on MC # 7, 8 & 9 (master climber)
Installation of TPO roofing continues on South Penthouse Roof continues.
Curtin wall #1 installation of framing to continues.
HSRB – I Vivarium Expansion:
Installation of Overhead plumbing pipe continues.
Site:
Layout of Plaza deck and installation of soils continues.