Construction Update - 7/9/21

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Locally, as the weekly number of new Covid cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.

This past week's (7/05/21 to 7/10/21) scheduled work activities:

G2

  • Pneumatic Tube system installation continues.

  • Radiopharmacy Hot Cell delivery of equipment underway.

  • Lead-lined drywall installation in Hot Cell complete.

G1

  • Pneumatic tube overhead rough- in continues.

  • Wall framing and in wall MEP rough- in continues.

  • Overhead MEP rough in continues.

  • Installation of Fire sprinkler hangers in BSL area is underway.

  • Installation of mezzanine steel plates continues.

Level 1

  • In Wall MEP Installation continues, cover up inspections also underway.

  • Overhead MEP installation continues.

  • Installation of scaffolding in atrium to support “dance floor” at top of atrium which will allow workers in work on atrium ceiling 6 stories above.

  • Installation of spray on fire proofing to underside of West Pedestrian bridge.

Level 2

  • Overhead MEP installation continues.

  • In wall MEP rough in continues.

  • Framing of soffits and hard ceiling areas continues in North Tower

Level 3

  • Overhead and in wall rough in of MEP Installation continues.

  • In wall MEP rough-in continues.

Level 4

  • Overhead MEP installation continues.

  • Fire suppression installation start – North Tower.

Level 5

  • Overhead MEP rough in continues.

  • Priority wall framing completed.

  • East pedestrian bridge detailing and decking with steel plate underway.

Level 6

  • Overhead MEP installation continues – North & South Towers.

  • Priority wall framing continues- South Tower.

  • Installation of the steel that supports the exterior “eyebrow” began – North Tower.

  • 6th floor East pedestrian bridge detailing continues.

  • Glass Curtain Wall framing on East façade.

Skin:

  • Glass Curtin Wall #2 glazing and trim East facade.

  • Glass Curtin wall #3 framing continues on West façade.

  • North facade granite and window installation continues.

  • CMU Installation – Level 2 & 3 South Tower.

  • “Eyebrow” steel support installation continues.

Next week's (7/12/21 to 7/17/21) scheduled work activities:

G2

  • Installation of Hydraulic Elevator (Elevator #3) continues

  • ADS Pit Lead brick installation continues.

  • Installation of lead-lined drywall in hot cell area will continues.

  • Pneumatic tube installation continues.

  • Radio pharmacy Hot Cell technicians arrive to begin installation of equipment.

G1

  • Pneumatic Tube Overhead rough-in continues

  • Overhead MEP Rough-in continues.

  • Wall Framing & in wall MEP rough- in continues.

  • Catwalk and mechanical mezzanine over BSL3 & ABSL3 areas continues.

  • Installation of fire suppression equipment hangers in BSL lab area continues.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • In wall blocking begins.

Level 2

  • Overhead & In wall MEP Installation continues.

  • Install soffits and ceiling framing – South Tower.

Level 3

  • Overhead MEP work continues.

  • Installation of metal decking on East Pedestrian bridge.

Level 4

  • Overhead MEP installation continues.

  • East pedestrian bridge detailing continues.

  • Fire Suppression equipment installation continues in North tower and starts in South Tower.

Level 5

  • Overhead MEP installation continues.

  • East pedestrian bridge detailing & decking.

Level 6

  • Overhead plumbing installation continues.

  • Priority wall framing installation – South Tower.

  • East pedestrian bridge detailing & decking.

Mechanical Penthouse

  • Installation of steel eyebrow supports continues.

Skin

  • Curtin wall #2 glazing & trim – East Façade.

  • Curtin wall #3 glazing – West Façade.

  • Curtin wall #4 framing – West Façade

  • Granite installation – Level 1 North Façade.

  • CMU installation Level 3 & 4 South Tower.

  • Marble prep on North Façade begins.

  • Eyebrow support Steel installation continues on North Facade



1 view0 comments