Construction - 11/13/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.


This past week's (11/09/20 to 11/14/20) scheduled work activities:


G2

  • Electrical and Plumbing Overhead Rough-In Continues

  • Backfill Continues around G2

G1

  • Electrical and Plumbing Overhead Rough-In Continues

  • Formwork Removal Under Pour 2 and 3

Level 1

  • Level 1 pour #6

  • Installing Formwork for Pour 8 and 9

  • Installing Plaza Waterproofing

  • Installing Reinforcing Steel on Pours 7 and 8

  • Pouring Foundation Wall

Next week's (11/16/20 to 11/21/20) scheduled work activities:

G2

  • Electrical and Plumbing Overhead Rough-In continues.

G1

  • Electrical and Plumbing Overhead Rough-In continues.

Level 1

  • Pouring Level 1 pour 5.

  • Pouring Level 1 pour 7

  • Installing rebar for pour 8.

Level 2

  • Installing formwork and columns for level 2 pour 1

Vivarium Expansion

  • installation of stone fill for new slab on grade floor



6 views0 comments