The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the management team feels that everyone on the job site can continue to work safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (7/13/20 to 7/18/20) scheduled work activities:
G2:
Complete remaining continuous footings
Backfill of foundation walls continues
Form Cyclotron lid
Subgrade preparation for slab on grade concrete pour in Area B
G1:
Install reinforcing and pour Utilidor footings
G2-G1 foundation wall south transition forming and rebar install
MEP UG installation continues
Next week's (7/20/20 to 7/24/20) scheduled work activities:
G2:
Form remainder of G2 Foundation Walls
Install slab reinforcing for Pour B
Backfill of foundation walls continues
G1:
Install reinforcing and pour Utilidor columns and walls
G2-G1 foundation wall south transition forming and rebar install
MEP UG installation continues
North continuous foundations forming and waterproofing install
Commenti