Construction Update - 12/20/19

This past week's (12/16 – 12/21) scheduled work activities.

  • Storm Line A continues under Brumley Bridge.

  • Storm Detention Piping for Storm Detention Line B continues to be delivered to site.

  • Excavation for Storm detention piping at B line and removal of dirt continue.

  • All dump trucks used on site have blue flag with white number on them to help identify them on the roads if neighbors want to register a complaint.

Next week's (12/23 – 12/28 ) scheduled activities.

  • Excavation and installation of storm detention Line B continues.

  • Job Site closed 12/24 & 12/25.

  • Next weekly report will be issued on 1/3/20.