This past week's (3/2/20 to 3/7/20) scheduled work activities:
Blast #21 was held on Monday 3/2/20, No blast on Wednesday 3/4 due to rain and no blast on Friday 3/6 due to previously scheduled Trump visit. US Secret Service advised we should cancel blast due to Trumps scheduled visit to CDC.
Last section of Storm line B to be installed on Friday/Saturday.
Site retaining wall work continues last section to be poured on Friday/Saturday.
Removal and salvage of marble on outside of Café continues.
Next week's (3/9/20 to 3/14/20) scheduled work activities:
Rock removal scheduled for Monday, Wednesday, & Friday.
Mass excavation of G-2 level will continue.
Excavation of G-1 level will begin.
Site retaining wall installation will be completed.
Long term look ahead activities:
Potholing in Haygood drive for new sanitary line installation is on hold because we are waiting on City of Atlanta permit to work in Haygood.
Erection of project tower crane has slipped another week to weekend of 3/28/20 - 3/29/20. This is caused because of our inability to excavate material where the base of crane is to be installed/poured.