top of page
  • Writer's pictureemoryhsrb2

Construction Update - 3/6/2020

This past week's (3/2/20 to 3/7/20) scheduled work activities:


  • Blast #21 was held on Monday 3/2/20, No blast on Wednesday 3/4 due to rain and no blast on Friday 3/6 due to previously scheduled Trump visit. US Secret Service advised we should cancel blast due to Trumps scheduled visit to CDC.

  • Last section of Storm line B to be installed on Friday/Saturday.

  • Site retaining wall work continues last section to be poured on Friday/Saturday.

  • Removal and salvage of marble on outside of Café continues.

Next week's (3/9/20 to 3/14/20) scheduled work activities:


  • Rock removal scheduled for Monday, Wednesday, & Friday.

  • Mass excavation of G-2 level will continue.

  • Excavation of G-1 level will begin.

  • Site retaining wall installation will be completed.

Long term look ahead activities:


  • Potholing in Haygood drive for new sanitary line installation is on hold because we are waiting on City of Atlanta permit to work in Haygood.

  • Erection of project tower crane has slipped another week to weekend of 3/28/20 - 3/29/20. This is caused because of our inability to excavate material where the base of crane is to be installed/poured.



30 views0 comments

Recent Posts

See All

Comments


bottom of page