top of page
  • Writer's pictureemoryhsrb2

Construction Update - 11/15/2019

This past week's (11/11 – 11/15) scheduled construction activities:

  • Completed removal of abandoned electrical manhole along Haygood Drive.

  • Continue installation of storm line A along Haygood Drive.

  • Continue leveling of site and removal of soil & miscellaneous abandoned underground utilities.

  • Resume line drilling near HSRB – I, in preparation for site work closer to HSRB – I. This will reduce possibility of vibrations affecting HSRB – II -- Equipment mobilized on site, drilling to begin on 11/18/19.

  • Construction of temporary road at SW corner of site, this road is in general location of where relocated Andrews circle will be constructed.

Next week's (11/18 – 11/22) construction activities:

  • Line drilling along edge of construction site closest to HSRB – I. Begins 11/18/19.

  • Continue installation of storm line A along Haygood and connection to existing storm line that runs under CSX railroad.

  • Continue leveling of site and removal of extra dirt from site.

  • Removal of holly trees near location of former outdoor café patio.



21 views0 comments

Recent Posts

See All
bottom of page