This past week's (11/11 – 11/15) scheduled construction activities:
Completed removal of abandoned electrical manhole along Haygood Drive.
Continue installation of storm line A along Haygood Drive.
Continue leveling of site and removal of soil & miscellaneous abandoned underground utilities.
Resume line drilling near HSRB – I, in preparation for site work closer to HSRB – I. This will reduce possibility of vibrations affecting HSRB – II -- Equipment mobilized on site, drilling to begin on 11/18/19.
Construction of temporary road at SW corner of site, this road is in general location of where relocated Andrews circle will be constructed.
Next week's (11/18 – 11/22) construction activities:
Line drilling along edge of construction site closest to HSRB – I. Begins 11/18/19.
Continue installation of storm line A along Haygood and connection to existing storm line that runs under CSX railroad.
Continue leveling of site and removal of extra dirt from site.
Removal of holly trees near location of former outdoor café patio.