Construction Update - 9/4/2020

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (8/31/20 to 9/5/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Continue Pouring continuous footings

  • Continue forming and pouring G1 Walls

  • Finish Forming and continue Rebar for Level 1 Pour 2

  • Backfilling around G2 and East side of G1

Level 1:

  • Level 1 Forming and Pouring grade beam in Pour 2

  • Waterproofing Pour 3

  • Grading for Pour 4


Next week's (9/7/20 to 9/12/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Form and prep for Pour 3

  • Slab on Grade Pour 3

  • Underground utilities for Slab on Grade Pour 4

  • Pour Wall in Pour 3

  • Prep wall in Pour 4