The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Effective Monday, August 9, 2021 Je Dunn will reinstitute/require the wearing of face masks on the job site. Additional new policy may be added in the future.
This past week's (8/30/21 to 9/04/21) scheduled work activities:
G2
Radiopharmacy Hot Cell Installation Continues.
Ceiling grid installation continues.
Low voltage wiring continues.
Light fixture installation continues.
Drywall finishing work continues.
Prep for installation of sheet vinyl flooring has begun.
prep for Installation of sheet epoxy flooring begins.
G1
Overhead and in wall MEP rough in continues.
Pressure decay duct testing in BSL3 lab areas continues.
Wall framing on perimeter of BSL 3 lab area and in DAR vivarium
Piping of Vivarium AHU 4.1 & 4.2 with Chilled water is underway.
Flush and fill of Chilled Water Systems has begun.
HEPA Filter Room Buildout continues.
Level 1
Electrical Busduct “A” and “C” Riser installation continues.
Level 2
Drywall one-side hanging complete – South Tower.
Hard Ceiling Rough in – North Tower underway.
Inwall and overhead insulation installation continues.
Level 3
Overhead and in wall rough in of MEP Installation continues.
Drywall one-side hanging continues – North Tower.
In-wall blocking and MEP insulation installation continues – South Tower.
Level 4
In wall MEP rough in continues.
Overhead MEP insulation installation continues.
In-wall blocking and MEP insulation continues – North Tower.
Level 5
Overhead MEP rough in continues.
Non-priority wall framing complete – North Tower.
Soffit framing continues -North Tower.
Level 6
Overhead MEP installation continues.
Mechanical Penthouse
Fireproofing underside of metal roof decking – North Tower.Installation of steel structures on South Tower Mechanical penthouses continues.
Installation of Parapet wall is underway on the North Tower Mechanical penthouse.
Skin:
Site:
Functional testing of backup generators is underway.
Next week's (9/06/21 to 9/11/21) scheduled work activities:
G2
Cyclotron epoxy flooring installation to begin.
Sheet vinyl flooring installation continues.
Installation of Radiopharm Hot Cells resumes.
Drywall finishing will continue.
Light fixture installation continues.
G1
Overhead MEP Rough-in continues.
In wall MEP rough- in continues.
Piping of AHU 4.1 & 4.2 with Chilled water continues.
Flush and fill of chilled water system begins/continues.
Wall framing in BSL 3 area continues and in Vivarium (ARL) area continues.
Ductwork testing in BSL3 area continues.
Piping of VAV’s on West side.
Final wall cover up begins is selected areas.
Level 1
Busduct A and C riser Installation continues.
In wall MEP installation.
Level 2
Hard Ceiling rough – in continues.
Installation of in wall and overhead insulation continues.
Level 3
Installation of Overhead & in wall MEP insulation continues.
Hard ceiling rough in begins.
Drywall one-side hanging North & South Tower continues.
Level 4
Installation of overhead MEP insulation continues.
In-wall MEP rough in continues.
Installation of MEP blocking and insulation continues.
Level 5
Non-Priority wall framings continues – South Tower.
Soffit framing continues on North Tower.
Level 6
Overhead MEP installation continues.
Mechanical Penthouse
Installation of fireproofing to underside of metal rood deck continues – North Tower
Installation of Metal decking (area 3) on South Penthouse roof continues
Installation/setting of the skylight steel begins.
Skin
Curtin Wall #3 Caulk & Trim – West Façade continues.
Installation of windows in punched openings continues – South Façade.
Marble installation starts at Northwest Façade.
Site:
Functional testing of generators will continues.