The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (9/14/20 to 9/19/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Concrete Slab Pour 2 Stone Fill
Concrete Slab Pour 4 Electrical Rough In
Concrete Slab Pour 4 Reinforcing
Concrete Slab Pour 4 Plumbing
Concrete Slab Pour 4 Waterproofing
Concrete pour at section of North foundation wall
Level 1:
Reinforcing for Elevated Concrete Deck Pour 4
Next week's (9/21/20 to 9/26/20) scheduled work activities:
G2:
Stripping of G1 Elevated Formwork
Re-shore Installation of G1 Elevated
Backfilling of G2 Continuous Foundation Walls Continue
G1:
Backfill of Slab on Grade Pour 4 East Complete
Backfill of Slab on Grade Pour 2 Starts
Installation rebar for West foundation wall next to HSRB – I continues.
Installation of Level G1 to 1 Columns over G1 Elevated Slab Deck
Waterproofing Slab on Grade Pour 4 East Starts
G1 Underground MEP Installation Continues
Level 1
Reinforcing for Level 1 Pour 2 Continues
Forming Level 1 Pour 4 Starts