top of page
  • Writer's pictureemoryhsrb2

Construction Update - 9/17/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Effective Monday, August 9, 2021 Je Dunn will reinstitute/require the wearing of face masks on the job site. Additional new policy may be added in the future.

This past week's (9/13/21 to 9/18/21) scheduled work activities:

G2

  • Radiopharmacy Hot Cell Installation Continues.

  • Stonhard Epoxy Flooring installation begins.

  • Light fixture installation continues.

  • Cyclotron Epoxy flooring installation underway

G1

  • Overhead and in wall MEP rough in continues.

  • Pressure decay duct testing in BSL3 lab areas continues.

  • Wall framing on perimeter of BSL 3 lab area and in DAR vivarium.

  • Fire Sprinkler installation under way in BSL & ABSL areas.

  • Flush and Fill of chilled water piping is underway.

Level 1

  • Electrical Busduct “A” and “C” Riser installation continues.

  • Restroom in wall and ceiling inspections underway.

Level 2

  • Hard Ceiling Rough in underway.

  • Inwall and overhead insulation installation continues.

Level 3

  • Overhead and in wall rough in of MEP Installation continues.

  • Drywall one-side hanging continues – South Tower.

  • In-wall MEP insulation installation continues – South Tower .

Level 4

  • In wall MEP rough in continues.

  • Overhead MEP insulation installation continues.

  • In-wall blocking and MEP insulation continues – North Tower.

Level 5

  • Overhead MEP rough in continues.

  • Non-priority wall framing continues – South Tower.

  • Soffit framing continues -North Tower,

Level 6

  • Overhead MEP installation continues.

Mechanical Penthouse

  • MEP Installation at underside of metal roof decking – North Tower.

  • Installation of steel decking on South Tower Mechanical penthouses ready for concrete pour.

  • Installation of ring beam underway at South Penthouse of South Tower.

  • Setting of the skylight Steel has begun.

  • Setting of final roof trusses took place.

  • Installation of Penthouse Mechanical equipment continues @ South Tower.

Skin:

  • Air & water barrier installation continues – South Façade.

  • Marble installation continues Level 5 Northeast Facade.

  • Installation of windows in punched openings on South Façade continues.

  • Granite installation on North Façade continues.

Site:

  • Functional testing of backup generators is underway.

Next week's (9/20/21 to 9/25/21) scheduled work activities:

G2

  • Stonhard flooring installation continues.

  • Sheet vinyl flooring installation continues.

  • Installation of Radiopharm Hot Cells continues.

  • Light fixture installation continues.

G1

  • Overhead MEP Rough-in continues.

  • In wall MEP rough- in continues.

  • Piping of AHU 4.1 & 4.2 with Chilled water continues.

  • Chilled water system final chemical treatment is performed.

  • Wall framing in Vivarium (ARL) area continues.

  • Branch ductwork testing in BSL3 area continues.

  • Installation of fire sprinklers in BSL3 areas continues.

  • Final wall cover up begins is selected areas

Level 1

  • Busduct A and C riser Installation continues.

  • Restroom drywall wall cover ups are underway.

Level 2

  • Hard Ceiling rough – in continues.

  • Installation of in wall and overhead insulation continues.

Level 3

  • Installation of Overhead & in wall MEP insulation continues.

  • Hard ceiling rough in begins.

  • Drywall one-side hanging continues.

Level 4

  • Installation of overhead MEP insulation continues.

  • In-wall MEP insulation continues.

  • Installation of MEP insulation continues – South Tower.

Level 5

  • Non-Priority wall framings continues – South Tower.

  • Installation of Phoenix values begins.

Level 6

  • Overhead MEP installation continues.

Mechanical Penthouse

  • Installation of Overhead MEP Continues – North Tower

  • Installation of Metal decking on South Penthouse roof continues.

  • Pouring of concrete decking on areas 3 &4 of South Penthouse.

  • Installation/setting of the skylight steel continues.

Skin

  • Air and Water Barrier installation -South Façade.

  • Installation punched window Aluminum surrounds continues.

  • Framing and Glazing of punched window openings continues on South Façade.

  • Marble installation starts at Northwest Façade.

  • Instalation of Vapor Barrier on North Mechanical penthouse begins (Weather Permitting).

Site:

  • Functional testing of generators will continues.



5 views0 comments

Recent Posts

See All
bottom of page