Construction Update - 8/14/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.


This past week's (8/10/20 to 8/15/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Pour G1 Slab on Grade – Area 1

  • Pour Elevated G1A Slab

  • Continue Forming G1B Elevated Slab

  • Preprufe Remaining Pile Caps

  • Install Sanitary Line Along Haygood

  • Continued G1 MEP Underground Rough-In

  • Forming Level 1 Elevated Slab

Next week's (8/17/20 to 8/21/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Continue Forming Level 1 Elevated Slab

  • Continued G1 MEP Underground Rough-In

  • Install BSL3 Underground Piping

  • Waterproofing and Reinforcing G1 Slab on Grade

  • Pour Continuous Footings and Foundation Walls