The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Effective Monday, August 9, 2021 Je Dunn will reinstitute/require the wearing of face masks on the job site. Additional new policy may be added in the future.
This past week's (8/09/21 to 8/14/21) scheduled work activities:
G2
Radiopharmacy Hot Cell Installation Continues.
Lead Brick placement occurring.
Pneumatic tube install continues.
Framing of hard ceilings in spaces has begun.
Drywall finishing work continues.
G1
Wall framing at perimeter of BSL suites continues
Overhead and in wall MEP rough in continues.
Pressure decay duct testing in BSL3 lab areas is underway.
Wall framing on perimeter of BSL 3 lab area and in DAR vivarium Pneumatic tube installation continues.
Multistack chiller delivery and installation.
Level 1
One sided Drywall installation underway – South Tower.
Level 2
Overhead MEP installation continues.
In wall MEP rough in continues.
Level 3
Overhead and in wall rough in of MEP Installation continues.
Level 4
In wall MEP installation and blocking continues.
Overhead MEP installation continues.
Level 5
Overhead MEP rough in continues.
Level 6
Overhead MEP installation continues.
6th floor East pedestrian bridge slab on metal deck pour was completed.
Mechanical Penthouse
Installation of steel structures on South Tower Mechanical penthouses continues.
Installation of detailing & decking is underway on the North Tower Mechanical penthouse.
Skin:
Site:
Installation of the concrete pad and gas meter is 95% completed.
View from South Tower Penthouse level looking to East at North Tower Penthouse Steel.
Next week's (8/16/21 to 8/21/21) scheduled work activities:
G2
Installation of Hydraulic Elevator (Elevator #3) continues.
Overhead MEP rough in will continue.
Pneumatic tube installation continues.
Drywall finishing will continue.
Hard ceiling installation will be completed.
G1
Overhead MEP Rough-in continues.
In wall MEP rough- in continues.
Catwalk and mechanical mezzanine over BSL3 & ABSL3 areas continues.
Wall framing in BSL 3 area continues and in Vivarium (ARL) area continues.
Ductwork testing in BSL3 area continues.
Level 1
Drywall one sided hanging will be completed – South Tower.
Level 2
Overhead & In wall MEP Installation continues.
Level 3
Overhead & in wall rough in of MEP work continues.
Installation of Insulation of overhead MEP components underway.
Level 4
Overhead MEP insulation continues.
In wall rough in of MEP begins.
Level 5
Overhead MEP insulation work continues.
Non-Priority Wall Framing – North Tower
Level 6
Overhead MEP installation continues.
Mechanical Penthouse
Structural steel decking installation continues – North Tower.
MEP inserts in Metal – North Tower.
Slab on metal dreck pour – North Tower.
Structural Steel Install continues on South Tower.
Skin
Curtin Wall #3 Caulk & Trim – West Façade continues.
Curtin Wall 4 Glazing continues – West Façade.
Marble installation – Level 2 Northeast Façade.
CMU installation Level 4 & 5 Southwest Facade.
Site:
7 week Commissioning efforts begin at Micro-grid.