The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Locally, as the weekly number of new Covid cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.
This past week's (6/28/21 to 7/03/21) scheduled work activities:
G2
Pneumatic Tube system installation underway.
ADS Pit Lead brick installation underway.
Hydraulic Elevator Installation underway.
Lead-lined drywall installation in Hot Cell area is concluding.
G1
Pneumatic tube overhead rough- in begins.
Wall framing and in wall MEP rough- in continues.
Overhead MEP rough in continues.
Office and elevator shaft wall framing continues.
Level 1
In Wall MEP Installation continues.
Overhead MEP installation continues.
Frame soffits and hard ceilings – South Tower, Area B.
Level 2
Overhead MEP installation continues.
In wall MEP rough in continues.
Framing of soffits and hard ceiling areas continues in North Tower
Installation of CMU exterior walls on South façade of South Tower continues.)
Level 3
Overhead and in wall rough in of MEP Installation continues.
Non-Priority walls – North Tower,
Installation of Fire suppression equipment – North Tower, Area D.
Detailing of East pedestrian bridge continues.
Level 4
Overhead MEP installation continues.
Detailing of East pedestrian bridges continues.
Exterior drywall framing continues on the South Tower
Level 5
Overhead MEP rough in continues.
Priority wall framing – South Tower.
Exterior drywall framing – South Tower.
East pedestrian bridge detailing begins.
Level 6
Overhead MEP installation – North & South Towers.
Exterior drywall framing- South Tower.
Installation of the steel that supports the exterior “eyebrow” began – North Tower.
East pedestrian bridge detailing underway.
Glass Curtain Wall framing on East façade.
Skin:
Glass Curtin Wall # 3 & #4 Stared on West Facade.
North facade granite installation continues.
CMU Installation – Level 3 & 4 South Façade.
Next week's (7/05/21 to 7/10/21) scheduled work activities:
The Job Site will be closed from COB on Friday, 7/2/21 until 6:00 AM on Tuesday, 7/6/21
G2
Installation of Hydraulic Elevator (Elevator #3) continues
ADS Pit Lead brick installation continues.
Installation of lead-lined drywall in hot cell area will continues.
Pneumatic tube installation at Hot cells continues.
Radio pharmacy Hot Cell Delivery of equipment begins.
Hanging additional dry wall in radio pharmacy area.
G1
Pneumatic Tube Overhead rough-in continues
Overhead MEP Rough-in continues.
Wall Framing & in wall MEP rough- in continues.
Catwalk and mechanical mezzanine over BSL3 & ABSL3 areas continues.
Installation of fire suppression equipment hangers in BSL lab area underway.
Level 1
Overhead MEP installation continues.
In wall MEP installation continues.
Level 2
Overhead & In wall MEP Installation continues.
Install soffits and ceiling framing – North Tower.
Installation of Temporary dry wall.
Level 3
Overhead MEP work continues.
Non-Priority walls- South Tower work to continue.
Installing fire suppression equipment- South Tower.
Level 4
Overhead MEP installation continues.
Installing of mechanical piping riser continues.
Fire Suppression equipment installation – South Tower.
Level 5
Overhead MEP installation continues.
Installation of steel piping in mechanical risers continues.
Priority wall framing to be completed.
Level 6
Overhead plumbing installation continues.
Priority wall framing installation – South Tower.
Pour North tower stairs (N1)
Mechanical Penthouse
Installation of steel eyebrow supports continues.
Skin
Granite installation along Andrews Circle will continue.
Curtin wall #2 installation on North Tower East L6 elevation to conclude.
South facade CMU installation L4 & L5 West continues.
Curtain Wall framing on West Façade Level 3 & 4.