The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (7/20/20 to 7/24/20) scheduled work activities:
G2:
Slab on grade Pour B reinforcing begins
Slab on grade Pour B MEP slab inserts install begins
Reinforcing install for remaining G2 foundation walls
G1:
Elevated slab Pour A forming begins
Utilidor reinforcing installed
Columns poured for Level 1 in southeast corner of G1
MEP underground install continues
Lean mix poured under north continuous foundations
Slab on grade Pour 1 subgrade preparation begins
Next week's (7/27/20 to 8/1/20) scheduled work activities:
G2:
Slab on grade Pour B reinforcing complete
Slab on grade Pour B pour
Forming and pouring of remaining foundation walls
G1:
Form and pour utilidor walls
Pour 1 slab on grade top mat rebar
Columns poured for Level 1 in southeast corner of G1 continues
Slab on grade Pour 1 reinforcing begins