top of page
  • Writer's pictureemoryhsrb2

Construction Update - 2/21/2020

This past week's (2/17/20 to 2/22/20) scheduled work activities:


  • Rock blasting was performed on Monday and Friday but cancelled on Wednesday due to weather.

  • Site retaining wall pours continue but were slowed by weather.

  • Deep excavations @ G-2 level continues.

  • Saw cutting of loading dock area in preparation of loading new fire line installation begins on Tuesday.




Next week's (2/24/20 to 2/29/20) scheduled work activities:


  • Rock removal scheduled for Monday, Wednesday, & Friday weather permitting.

  • Additional deep excavation and dirt removal will continue at G-2 level.

  • Site retaining wall forming and pouring of concrete footings will continue.


Long term look-ahead activities:


  • Potholing in Haygood drive for new sanitary line installation is on hold because we are waiting on City of Atlanta permit to work in Haygood.

  • Erection of project tower crane has slipped 1 week to weekend of 3/21/20 - 3/22/20.

11 views0 comments

Recent Posts

See All
bottom of page