top of page
  • Writer's pictureemoryhsrb2

Construction Update - 2/12/21

Updated: Mar 2, 2021



The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the team feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week’s (2/08/21 to 2/13/21) scheduled work activities:


G2

  • Overhead MEP work continues.

  • Layout of walls continues.

  • Stairs were set in place between levels G2 and G-1.

G1

  • Overhead MEP Rough-In Continues.

  • Layout of walls continues.

Level 1

  • Removal of reshores at Level 1 Pour 2.

Level 3

  • Forming and pouring of column from Levels 3 to 4 Continues.

Level 4

  • Electrical in slab rough in continues.

  • Framing and Decking installed for Level 4 Pour 3 & 4.

  • Concrete pour on Level 4 areas 1 & 2 were completed.

Site

  • Poured Retaining Wall #2.

  • Installation of Grease trap.

  • Work on exterior mock up continues .

  • Installation for Electrical duct bank from Microgrid to building continues

Next week’s (2/15/21 to 2/20/21) scheduled work activities:


G2 & G1

  • Overhead MEP rough-in continues

  • Layout of interior walls continues.

  • Pour ramp slab

Level 1

  • Removal of reshores at Level 1 Pour 3.

Level 3

  • Forming and pouring of last few remaining columns.

Level 4

  • Framing for columns level 4 to 5 begins.

  • Pouring of slabs in areas 4-3 & 4-4 (these were originally schedule for this past week but delayed due to rain).

Level 5

  • Forming of decking for Level 5 areas 1 & 2 continues.

Site

  • Finish D-Line Storm line work and begin backfilling.



13 views0 comments

Recent Posts

See All
bottom of page