Construction Update -12/17/2021


The HSRB – II job site will be closed on Friday, 12/25/21 & 12/31/21 for the holidays.

There will be no weekly construction updates on 12/25/21 & 12/31/21.

The next project update report will be distributed on 1/7/22.

The HSRB- II team wishes everyone a safe and happy holiday season!

This past week's (12/13/21 to 12/18/21) scheduled work activities:

G2

  • Hamilton Biorepository materials shipped to site and begin mobilization for install.

  • H2I remobilize to complete installation.

  • GE Cyclotron Mobilize materials and install.

  • Radiotracer and Hotcell installation continues.

G1

  • Hanging/Installation of Doors in back of house areas of G-1.

  • Closing in and finishing walls – BSL – South.

  • Framing of Wonder Wall in G1 Lobby continues.

  • Finishing of walls, floors, and door frames on G-1 Isolation rooms.

Level 1

  • Hanging and finishing walls and ceilings – South Tower.

  • Hanging remaining drywall – North Tower.

  • Installation of Community bathroom partitions is underway.

  • Installation of flooring in South Tower Lab Neighborhoods is underway.

Level 2

  • Lab lighting and service panel installations- South Tower.

  • Hanging and Finishing drywall – South Tower.

  • Prime & first coat of paint – South Tower .

Level 3

  • Installation of office & corridor lighting fixtures.

  • Installation of Lab lighting, service panels, and lighting control cables.

  • Wall inspections – Southwest.

Level 4

  • North Offices & Corridor lighting installation continues.

  • Installation of plumbing fixtures in community restrooms is underway.

  • installation of fireproofing on Est connector bridges.

Level 5

  • Installation of fan coil units is underway.

Level 6

  • Installation of “eyebrow” steel on exterior level 6 South Tower continues.

  • Installation of Steel decking on eyebrow continues.

  • Non-priority wall framing continues at South tower.

  • Installation of steel for stairs in atrium has begun.

Mechanical Penthouse

  • MEP Installation continues in South & North towers.

  • Hanging of walls on South Tower continues.

  • Continue framing and sheathing of Atrium Skylight structure.

Skin:

  • Marble installation continues on the South Tower.

  • Installation of marble on MC #6 continues at SW corner continues. Installation of TPO roofing on South Penthouse roofs continues.

  • Installation of the CMU walls of the East Stair tower continues.

  • Installation of steel framing for curtain wall #1 is underway.

HSRB – I Vivarium Expansion:

  • Concrete was poured on top of metal roof deck morning of Friday, 12/17/21

Site:

  • Lay out of planting and sidewalk areas on plaza deck has begun.

Next week's (12/20/21 to 12/25/21) scheduled work activities:

G2

  • Installation of radiotracer hot cells continues.

  • GE Cyclotron mobilize materials.

  • Hamilton Biorepository installation continues.

  • H2I installation continues.

G1

  • Closing in and finishing walls – BSL South.

  • Continue framing for wonder wall in lobby area.

  • Inspections in imaging area and closing of walls.

Level 1

  • Hanging remaining drywall in North tower.

  • Hanging and finishing drywall walls and ceilings- South tower.

  • Bathroom Partition Installation underway.

Level 2

  • Installation of lab lighting and service panels in South Tower continues.

  • Hanging and finishing walls – South.

  • Primer coat & first coat of paint – South.

Level 3

  • Installation of office and corridor lighting.

  • Installation of lab lighting, Service panels, and control wiring.

  • Wall Inspections – Southwest.

Level 4

  • Installation of lighting in corridors & offices in North Tower continues.

  • Installation of plumbing fixtures in community restrooms.

  • Fireproofing of East connector bridges continues.

Level 5

  • Installation of fan coil units.

Level 6:

  • Installation of eyebrow steel continues South Tower.

  • Non-priority wall framing continues – South Tower.

  • Installation of metal deck on top of eyebrow continues.

  • Fireproofing of interior of eyebrow continues.

Mechanical Penthouse

  • Installation of overhead MEP Continues – North & South Towers

  • Hanging of walls South.

  • Continue framing and sheathing of Skylight walls.

Skin

  • Marble installation continues on MC # 6, 7 & 8 (master climber)

  • Installation of TPO roofing continues on South Penthouse Roof.

  • Curtin wall #1 installation of framing to continue.

HSRB – I Vivarium Expansion:

  • layout for interior walls to begin.

Site:

  • Layout of Plaza deck to continue.