The HSRB – II job site will be closed on Friday, 12/25/21 & 12/31/21 for the holidays.
There will be no weekly construction updates on 12/25/21 & 12/31/21.
The next project update report will be distributed on 1/7/22.
The HSRB- II team wishes everyone a safe and happy holiday season!
This past week's (12/13/21 to 12/18/21) scheduled work activities:
G2
Hamilton Biorepository materials shipped to site and begin mobilization for install.
H2I remobilize to complete installation.
GE Cyclotron Mobilize materials and install.
Radiotracer and Hotcell installation continues.
G1
Hanging/Installation of Doors in back of house areas of G-1.
Closing in and finishing walls – BSL – South.
Framing of Wonder Wall in G1 Lobby continues.
Finishing of walls, floors, and door frames on G-1 Isolation rooms.
Level 1
Hanging and finishing walls and ceilings – South Tower.
Hanging remaining drywall – North Tower.
Installation of Community bathroom partitions is underway.
Installation of flooring in South Tower Lab Neighborhoods is underway.
Level 2
Lab lighting and service panel installations- South Tower.
Hanging and Finishing drywall – South Tower.
Prime & first coat of paint – South Tower .
Level 3
Installation of office & corridor lighting fixtures.
Installation of Lab lighting, service panels, and lighting control cables.
Wall inspections – Southwest.
Level 4
North Offices & Corridor lighting installation continues.
Installation of plumbing fixtures in community restrooms is underway.
installation of fireproofing on Est connector bridges.
Level 5
Installation of fan coil units is underway.
Level 6
Installation of “eyebrow” steel on exterior level 6 South Tower continues.
Installation of Steel decking on eyebrow continues.
Non-priority wall framing continues at South tower.
Installation of steel for stairs in atrium has begun.
Mechanical Penthouse
MEP Installation continues in South & North towers.
Hanging of walls on South Tower continues.
Continue framing and sheathing of Atrium Skylight structure.
Skin:
Marble installation continues on the South Tower.
Installation of marble on MC #6 continues at SW corner continues. Installation of TPO roofing on South Penthouse roofs continues.
Installation of the CMU walls of the East Stair tower continues.
Installation of steel framing for curtain wall #1 is underway.
HSRB – I Vivarium Expansion:
Concrete was poured on top of metal roof deck morning of Friday, 12/17/21
Site:
Lay out of planting and sidewalk areas on plaza deck has begun.
Next week's (12/20/21 to 12/25/21) scheduled work activities:
G2
Installation of radiotracer hot cells continues.
GE Cyclotron mobilize materials.
Hamilton Biorepository installation continues.
H2I installation continues.
G1
Closing in and finishing walls – BSL South.
Continue framing for wonder wall in lobby area.
Inspections in imaging area and closing of walls.
Level 1
Hanging remaining drywall in North tower.
Hanging and finishing drywall walls and ceilings- South tower.
Bathroom Partition Installation underway.
Level 2
Installation of lab lighting and service panels in South Tower continues.
Hanging and finishing walls – South.
Primer coat & first coat of paint – South.
Level 3
Installation of office and corridor lighting.
Installation of lab lighting, Service panels, and control wiring.
Wall Inspections – Southwest.
Level 4
Installation of lighting in corridors & offices in North Tower continues.
Installation of plumbing fixtures in community restrooms.
Fireproofing of East connector bridges continues.
Level 5
Installation of fan coil units.
Level 6:
Installation of eyebrow steel continues South Tower.
Non-priority wall framing continues – South Tower.
Installation of metal deck on top of eyebrow continues.
Fireproofing of interior of eyebrow continues.
Mechanical Penthouse
Installation of overhead MEP Continues – North & South Towers
Hanging of walls South.
Continue framing and sheathing of Skylight walls.
Skin
Marble installation continues on MC # 6, 7 & 8 (master climber)
Installation of TPO roofing continues on South Penthouse Roof.
Curtin wall #1 installation of framing to continue.
HSRB – I Vivarium Expansion:
layout for interior walls to begin.
Site:
Layout of Plaza deck to continue.