The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Effective Monday, August 9, 2021 Je Dunn will reinstitute/require the wearing of face masks on the job site. Additional new policy may be added in the future.
This past week's (10/04/21 to 10/09/21) scheduled work activities:
G2
Cyclotron was delivered and is being installed.
Stonhard Epoxy Flooring installation continues.
Overhead punch continues
Hot cell installation continues.
G1
Vivarium wall and ceiling framing continues.
Wall framing begins- BSL - South
Vivarium wall rough in continues in North Area.
Marble installation continues on North Tower Level 1
Level 1
Lab Neighborhood wall & ceiling cover up underway.
Community restroom hard ceiling cover up underway.
Level 2
Erection of steel for East connector bridges underway.
Cover up of walls in PI offices in North Tower underway.
Level 3
Hard ceiling and wall inspections of PI Offices North Tower underway.
Lighting rough-in continues – South Tower .
Level 4
Lighting Rough-in in North Tower underway.
Overhead MEP insulation installation continues.
In-wall insulation continues.
Level 5
One siding of drywall in North Tower.
Soffit framing/top out – South Tower.
MEP rough -in continues South tower.
Level 6
Overhead MEP installation continues.
Non-Priority wall framing continues in North Tower.
Installation of VAV units has begun in South Tower.
Mechanical Penthouse
MEP Installation continues in South tower.
Installation of vapor barrier roofing layer on North Tower Mechanical roof is underway.
Exterior framing & sheathing continues on South tower.Installation of spray on fireproofing of beams & columns in South Mechanical penthouse.
Setting of the steel for Atrium skylight on penthouse roof continues.
Skin:
Marble installation and caulking on Northeast & Northwest Façades continues.
Installation of windows in punched openings on South Façade continues.
Granite installation on Northwest Façade continues.
Site:
Functional testing of backup generators continues.
Next week's (10/11/21 to 10/16/21) scheduled work activities:
G2
Installation of Cyclotron continues.
Closing of opening in cyclotron wall.
Installation of radio-pharmacy Hot cells continues.
G1
Vivarium wall and ceiling framing will continues.
Wall framing continues BSL area – North.
Wall and ceiling cover – up will begin in vivarium South area.
Level 1
Lab Neighborhood wall and ceiling cover up underway.
Single restroom hard ceiling cover – up begins.
Level 2
Erection of steel for east connector bridge continues.
Lab Neighborhood wall & hard ceiling cover up – North Tower.
Wall cover up underway in North Offices, North Tower.
Level 3
Lighting rough – in continues in South Tower.
Level 4
Installation of overhead MEP insulation continues.
In-wall MEP insulation continues.
Lighting Rough - in – North Tower.
Detailing work on East connector bridge.
Level 5
One siding of drywall – North & South Towers.
Level 6
Overhead MEP installation continues.
Non-Priority wall framing continues – North Tower.
Start installation of Phoenix values underway.
Mechanical Penthouse
Installation of Overhead MEP Continues – North & South Towers
Pouring of concrete decking on South Penthouse.
Detailing of the skylight steel continues.
Exterior framing and sheathing of South penthouse continues.
Air & water barrier installation on exterior sheathing of North Tower.
Skin
Air and Water Barrier installation continues.
Framing and Glazing of punched window openings continues on South Façade.
Marble installation continues on Northwest & Northeast Façade.
Grouting Balcony’s on Level 2 to Level 6.
Installation of Vapor Barrier on North Mechanical penthouse will continue (Weather Permitting).
Site:
Functional testing of generators will continues for 1 more week.
Comments