This past week's (12/30/19 – 1/4/20) scheduled work activities.
Storm Line A installation was completed.
Excavation for Storm detention system along B line (under Andrews Circle) was completed.
Excavation included rock removal in area of storm detention system @ B Line.
Installation of Storm detention piping began.
Line drill of rock in building footprint resumed.
Site was closed on 1/1/20.
Next week's (1/6/20 – 1/11/20) scheduled construction activities.
Continued work on installation of storm detention system along B line.
Connection of storm detention system to existing storm line begins.
Resumption of rock removal activities on Monday, 1/6/20, Wednesday, 1/8/20, and Friday, 1/10/20 @ 4:30 PM each day.
Kommentare