Construction Update - 1/3/20

This past week's (12/30/19 – 1/4/20) scheduled work activities.

  • Storm Line A installation was completed.

  • Excavation for Storm detention system along B line (under Andrews Circle) was completed.

  • Excavation included rock removal in area of storm detention system @ B Line.

  • Installation of Storm detention piping began.

  • Line drill of rock in building footprint resumed.

  • Site was closed on 1/1/20.

Next week's (1/6/20 – 1/11/20) scheduled construction activities.

  • Continued work on installation of storm detention system along B line.

  • Connection of storm detention system to existing storm line begins.

  • Resumption of rock removal activities on Monday, 1/6/20, Wednesday, 1/8/20, and Friday, 1/10/20 @ 4:30 PM each day.