This past week's (1/03/22 to 1/08/22) scheduled work activities:
G2
Electrical connections.
Installation of Mechanical fittings.
Elevator 4 sump pump installation.
H2I remobilize to complete installation.
Installation of ACT grid is underway.
G1
Hanging/Installation of Drywall.
Primer and First coat of paint in South Offices.
Installation of cable trays in hallways.
Continue with installation of catwalk in BSL3 area.
Framing work continues at Wonder Wall.
Installation Of Shielding for 7T MRI continues.
Level 1
Hanging of ACT grid in South area.
Primer and 1st coat of finish paint in North offices.
Installation of selected casework has begun.
Level 2
Electrical System trim out of fixtures.
Hanging and Finishing drywall – North Tower.
Level 3
Finishing drywall in South Tower.
Pull electrical wiring South Tower.
Level 4
Hanging drywall South Tower.
Plumbing fixtures installed in community restrooms.installation of fireproofing on Est connector bridges.
Level 5
Installation of framing for supports of horizontal glass hangrailings.
Level 6
Installation of fan coil units and insulation in North Tower.
Mechanical Penthouse
MEP Installation continues in South & North towers.
running of electrical and control wires to AHU’s.
Continue framing and sheathing of Atrium Skylight structure.
Skin:
HSRB – I Vivarium Expansion:
Concrete has poured on top of metal roof deck.Hanging to temp work lights in new space.Contractor preparing to make utility connections into new space in coming weeks/months.
Site:
Lay out of planting and sidewalk areas on plaza deck has begun.Installation of soils for plaza area is also underway.
Next week's (1/10/22 to 1/14/22) scheduled work activities:
G2
Installation of Air distribution equipment continues.
Installation of lighting fixtures continues.
Hamilton Biorepository installation continues.
H2I installation continues.
G1
Installation of mechanical values at Catwalk continues.
Continue framing for wonder wall in lobby area.
Installation of conduit and electrical fixtures continues at catwalk.
Drywall finishing in corridors, mezzanine, and 7T room continues.
Installation of ACT ceilings in South offices continues.
Level 1
Hanging ACT ceilings in North tower.
Layout and framing of granting garden wall.
Primer and 1st coat of finish paint on North Tower.
Level 2
Ductwork rough-in at East Connector Bridges.
Atrium Glass Wall headers installed.
Level 3
Finishing drywall – South.
Hanging Drywall – North.
Installation of lab lighting, Service panels, and control wiring- South.
Installation of Steel for Monumental Stairs continues.
Level 4
Electrical trim out of fixtures for hanging of ACT ceilings in – South Tower.
Hanging Drywall in – South Tower.
Level 5
Installation of “shoes” for Atrium Glass wall.
Level 6
Installation of eyebrow drains.
Installation of fan coil units in North Tower.
Mechanical Penthouse
Start up of AHU 1.3 in South Mechanical penthouse.
Setting Glass -Roof Level.
Continue framing and sheathing of Skylight walls.
Skin
Marble installation continues on MC # 7, 8 & 9 (master climber)
Installation of TPO roofing continues on South Penthouse Roof.
Curtin wall #1 installation of framing to continues.
HSRB – I Vivarium Expansion:
Installation of Overhead plumbing pipe begins in new space.
Site:
Layout of Plaza deck and installation of soils continues.
Comments