Dec 17, 2020
Construction - 11/13/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 6, 2020
Construction Update - 11/06/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 10/30/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 10/16/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 10/2/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 9/25/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 9/18/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 9/11/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Nov 5, 2020
Construction Update - 9/4/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Aug 28, 2020
Construction Update - 8/28/2020
This past week's (8/24/20 to 8/29/20) scheduled work activities: G2: No major construction activities on level G-2 because this level is...


emoryhsrb2
Aug 28, 2020
Construction Update - 8/21/2020
This past week's (8/17/20 to 8/22/20) scheduled work activities: G2: No major construction activities on level G-2 because this level is...


emoryhsrb2
Aug 28, 2020
Construction Update - 8/14/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Aug 10, 2020
Construction Update - 8/7/2020
The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jul 31, 2020
Construction Update - 7/31/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jul 23, 2020
Construction Update - 7/23/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jul 13, 2020
Construction Update - 7/10/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jul 7, 2020
Construction Update - 7/3/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jul 1, 2020
Construction Update - 6/26/2020
This past week's (6/22/20 to 6/27/20) scheduled work activities: G2: Continuous footings & foundation walls continue Installation of...


emoryhsrb2
Jun 24, 2020
Construction Update - 6/12/2020
This past week's (6/8/20 to 6/13/20) scheduled work activities: G1 Level: Spread footings & columns continue Continuous footings &...


emoryhsrb2
Jun 24, 2020
Construction Update - 6/5/2020
This past week's (6/1/20 to 6/6/20) scheduled work activities: G2 Level: Continuous footings & foundation walls continue Pour Elevator 5...